The long-awaited closure to through traffic at the intersection of Airline Highway and Sunnyslope Road is set to start later today.
Council of San Benito County Governments' Transportation Planning Manager Mary Dinkuhn confirmed that crews are finishing up "last-minute" preparations and should get started - prompting the closure and detour - later today.
The detour is expected to last until around Aug. 20 and will allow construction crews from Graniterock Pavex to complete one of the final steps in the $49 million Highway 25 bypass project.
COG's detour allows traffic to proceed around the construction work by turning right in each direction, but not directly through the intersection. It also emphasizes the use of Ladd Lane and Hillock Drive to avoid congestion around the construction zone.
When opened, set for October, the bypass will reroute Highway 25 traffic through Hollister's east side instead of downtown on San Benito Street.
The work had been scheduled to start in May. Officials delayed it several times so utility companies could move power lines that were in the way.
The Free Lance Staff Got a question or a comment? Send us an email.
Although the Hollister Free Lance does not have any obligation to monitor this board, the Hollister Free Lance reserves the right at all times to check this board and to remove any information or materials that are unlawful, threatening, abusive, libelous, defamatory, obscene, vulgar, pornographic, profane, indecent or otherwise objectionable to the Hollister Free Lance in our sole discretion and to disclose any information necessary to satisfy the law, regulation, or government request. The Hollister Free Lance also reserves the right to permanently block any user who violates these terms and conditions. All threats to systems or site infrastructure shall be assumed genuine in nature and will be reported to the appropriate law enforcement authorities. Submission of any comments will be considered permission to use online or in print.